Egyptian Global Logistics (EGL) successfully delivered 2 Gearboxes and 2 Transformers from Adabiya port in Suez to Beni Sweif cement factory after storage in port yard using Beams and steel support.
Each unit travelled a total distance of 280 kms using 10 axle lines of a Goldhofer modular trailer.
Weighting 78 tons with 3.40 m height, 6.90 m long.
however, the major challenge was the 6.90 m width, as the basic route involves a number of narrow roads and obstacles. EGL overcame obstacles and tight schedules, solving the challenges in the safest and most cost-effective technique. Through careful planning, precise manoeuvring and absolute precision, EGL was able to transport the units safely to the factory site. Thanks to EGL Project Team for the cooperation, EGL continue to impress the market with the well-trained staff along with the latest fleet equipment in Egypt.